Ingleside Energy Center Terminal EPC Project

Project Summary

Saulsbury completed the engineering, procurement, and construction for a 100,000-bbl HD-5 propane loading terminal.

Major Equipment

  • Inlet meter skid
  • Regen liquid vaporizer
  • Regen gas superheater
  • Two propane driers
  • Two — 44,000-bbl storage spheres
  • Two — 50-horsepower propane transfer pumps
  • Three — 100,000-bbl loading arms
  • Two BOG compressors
  • Diesel-driven fire water pumps with two jockey pumps
  • 9.79-MMBtu/hr hot oil system

Key Quantities

  • 1,314 cubic yards of concrete
  • 478 drill piers
  • 374 tons of structural steel
  • 77,780 weld inches (underground and aboveground pipe)
  • 32,295 linear feet of pipe (above and below ground)
  • 67 pressure test packages
  • 36,290 linear feet of conduit
  • 276,335 linear feet of cable
  • 14,770 linear feet of cable tray
  • 12,378 terminations
  • 218 instruments
  • 450 loop checks

 