Refining and Carbon Kiln Facility Upgrade

Project Summary

Saulsbury was contracted for the electrical and instrumentation upgrades of a refining and carbon kiln facility for a client’s central Colorado gold mine. Work consisted of more than 5,400 tons of structural steel along with one gyratory crusher, three cone crushers, 2,100 conveyors, and miscellaneous equipment.

We were also subcontracted to complete the electrical and instrumentation work associated with the structural steel, tankage, piping, and mechanical work to facilitate the expansion of the existing gold recovery system.

Looking for more information?

Contact Us