Project Summary

Saulsbury was responsible for all aspects of the installation of underground piping, grounding and duct banks, concrete foundations, and buildings for the effluent water treatment system of a cheese manufacturing facility in Clovis, New Mexico. Approximately 3,000 linear feet of pipe and 1,100 cubic yards of concrete were installed on the project.

Scope of the Project

  • Backfill at liner key
  • Trenching and backfilling for buried piping
  • Pipe assembly and installation
  • Soil compaction testing
  • Subsurface chambers
    • Sand Filter (21 feet deep)
    • Waste Sludge
  • 260-cubic yard clarifier slab on a 70-degree slope
  • Foundation pads for equipment structures and pipe supports
  • Concrete testing
  • LRAL lagoon curb and miscellaneous structures

Goals and Accomplishments

The project was completed with zero incidents.