Construction of Linear Low-Density Polyethylene Plant in Odessa, Texas

Project Summary

Saulsbury provided all engineering, procurement, and construction services for the substations and motor control centers of a grassroots 200 MM LB/year linear low-density polyethylene plant. They also provided the electrical and instrumentation personnel needed. The project included the installation of medium and low-voltage feeders to approximately 300 various loads and motors within the unit.

Our construction personnel also performed the grassroots construction of 138-15 kilovolt, 20 MA substation, and two motor control center buildings.

Scope of the Project

Installation included:

  • Major transformers
  • High-voltage switching equipment
  • 15 kV, 5 kV, and 480-volt switchgear
  • 5kV and 480-volt starters
  • Step-down transformers and building power
  • Cable tray
  • Conduit
  • Wire and tubing for a DCS for 300 new instruments
  • Lighting
  • HVAC